Harbison #4 PS Improvements & Force Main Replacement
Project Map: View Project Map
Project Type: Force Main
Project Phase: Design & Permit
Project Description:
This project involves the evaluation of Pump Station (PS) improvement alternatives, evaluation of 3,500 LF of 6-inch PVC Force Main (FM) rehabilitation/ replacement alternatives, and preparation of a Preliminary Engineering Report (PER). The findings from PER stated that the PS and FM are adequately sized and functioning properly for the service area; however, the PS is receiving excess flow. City is pursuing to find and fix the source of excess flow before continuing with this project and it has been put on hold.
Council District: I
Sewer Basin: Broad River
Public Benefit: Efficient Operations; Environmental; Regulatory Compliance.
Project Map
Project Gallery

- Under Design.
- Estimated Design Completion Fall 2026.
- Estimated Construction Start Summer 2027.
- Estimated Construction Completion Spring 2028.