Harbison #4 PS Improvements & Force Main Replacement
Project Map: View Project Map
Project Type: Force Main
Project Phase: Design & Permit
Project Description:
This project involved evaluating Pump Station (PS) improvement alternatives and preparing a Preliminary Engineering Report (PER). The preliminary PER findings indicate that the PS may be adequately sized but is still receiving excess flow. The City completed a find-and-fix project to eliminate the source of excess flow into the PS. Improvements to the PS, such as constructing a larger and deeper wet well and increasing pump capacity, are currently underway.
Council District: I
Sewer Basin: Broad River
Public Benefit: Efficient Operations; Environmental; Regulatory Compliance.
Project Map
Project Gallery

- Under Design.
- Estimated Design Completion Spring 2027.
- Estimated Construction Start Fall 2027.
- Estimated Construction Completion Summer 2028.