Mill Creek PS Miscellaneous Improvements
Project Map: View Project Map
Project Type: Pump Station
Project Phase: Construct
Project Description:
Miscellaneous improvements at the Mill Creek Pump Station including the replacement of the four existing drywell pumps with new PLC and VFDs, installation of an HVAC system for the entire first (top) floor of the pump station, improvements to air-circulation within the sub floors, installation of a single stall restroom with a sink, construction of a steel platform adjacent to the existing grinder structure for housing bypass pumps, and regrading the yard area and site lighting improvements.
Council District: Outside
Sewer Basin: Mill Creek
Public Benefit: N/A
Project Map
Project Gallery

- Under Construction.
- Estimated Construction Completion Summer 2028.