Mill Creek PS Miscellaneous Improvements
Project Map: View Project Map
Project Type: Pump Station
Project Phase: Construct
Project Description:
This project includes miscellaneous improvements at the Mill Creek Pump Station: replacing the four existing dry-well pumps and installing new programmable logic controllers (PLCs) and variable-frequency drives (VFDs); installing an HVAC system for the entire first (top) floor of the pump station; improving air circulation within the lower floors; installing a single-stall restroom with a sink; constructing a steel platform adjacent to the existing grinder structure to house bypass pumps; regrading the yard area; and improving site lighting.
Council District: Outside
Sewer Basin: Mill Creek
Public Benefit: N/A
Project Map
Project Gallery

- Under Construction.
- Estimated Construction Completion Summer 2028.