East Rocky Branch Improvements Phase 1
Project Map: View Project Map
Project Type: Gravity Sewer
Project Phase: Construct
Project Description:
The East Rocky Branch Sewer Improvements Phase 1 (Upper Phase) project consists of upsizing the existing piping for a distance of approximately 7,500 linear feet with new 36-inch diameter gravity sewer, generally located along Rocky Branch. The project begins in the Five Points area at the intersection of Santee Ave and Harden St and terminates at the intersection of Main St and Whaley St. This project was identified as part of the collection system hydraulic modeling study (Hazen and Sawyer, 2014).
Council District: II & III
Sewer Basin: Rocky Branch
Public Benefit: Development Opportunity; Environmental; Regulatory Compliance.
Project Map
Project Gallery

- Under Construction.
- Estimated Phase 1 Construction Completion Summer 2028.