Skip to main content

Project ID: SS733101

Upper Kinley Creek Sewer Improvements

Project Map: View Project Map
Project Type: Gravity Sewer
Project Phase: Construct

Project Description:

This project proposes the replacement of sanitary sewer piping to upsize the existing piping from Manhole 19449MH to Manhole 25145MH for a distance of approximately 5,500 linear feet with new 24-inch diameter gravity sewer located along Kinley Creek from Harbison Boulevard to Piney Grove Road. This project was identified as part of the collection system hydraulic modeling study (Hazen and Sawyer, 2014). This project is classified as a capital investment because it includes the installation of new sewer lines.


Council District: I
Sewer Basin: Saluda River
Public Benefit: Development Opportunity; Environmental; Regulatory Compliance.

Project Map

Project Gallery

Council approved design 3/15/16. Council approved contract amendment #4 11/17/20. Council approved construction 5/16/23.
  • Pending Project Close Out.
Name: Sewer Line Capacity Enhancement Drop-In - Upper Kinley Creek Date: 9/22/2016 Time: 5:00 - 7:00 Location: McGregor Presbyterian Church - McGregor Hall