A Program Of The

City Of Columbia

Project Description: The purpose of this project is to replace approximately 1,700 linear feet of 6-inch ductile iron and cast iron force main. The force main has been identified as needing replacement from the Shady Lane Pump Station to the discharge manhole on Shady Lane. Tasks included under this project include preliminary design, final design, permitting, easement exhibits, bidding assistance, construction inspection, and general services support during construction of the force main replacement.  Total Current Contract Value is $119,515.00.

Public Benefit: Environmental; Regulatory Compliance.

Project Map Project Gallery
  • Project Status
  • Project Schedule
  • Project Events
Submitted to procurement.
Estimated Design Start Summer 2020.
Name Date Time Location Area
FOOTER COMING SOON