Project Description: This project proposes the installation of parallel sewer piping along the existing Crane Creek outfall as a relief sanitary sewer piping system from the Manhole SS-CC02-24427-MH (downstream extent of Lower Crane Creek Relief Sewer Phase 1 – CIP38) to the North Columbia Pump Station for a distance of approximately 12,900 linear feet of 48-inch gravity sewer and approximately 7,600 linear feet of 54-inch gravity sewer. Total Current Contract Value is $4,000,000.00.

  • Council District: I & Outside
  • Sewer Basin: Crane Creek

Public Benefit: Development Opportunity; Environmental; Regulatory Compliance.

Project Map Project Gallery
  • Project Status
  • Project Schedule
  • Project Events
In preparation for submission to procurement.
Estimated PER Start Spring 2019.