Project Description: Major improvements to reduce I/I in system and eliminate stormwater discharges into sewer system. Sub basin consists of 800 manholes and 145,702 linear feet of gravity sewer line, many of which will be rehabilitated as part of this project. Total Current Contract Value is $10,248,818.27.

Public Benefit: Environmental; Regulatory Compliance.

Project Map Project Gallery
  • Project Status
  • Project Schedule
  • Project Events
Council approved design 5/17/16. Council approved CA#1 5/1/18. Council approved construction 5/1/18. NTP for construction issued 6/1/18.
Under Construction.

Estimated Construction Completion Summer 2019.