Project Description: Major improvements to reduce I/I in system and prevent stormwater discharges into sewer system. Total Current Contract Value is $6,405,166.12.

Public Benefit: Cost Effective; Environmental; Regulatory Compliance.

Project Map Project Gallery
  • Project Status
  • Project Schedule
  • Project Events
Council approved design 8/19/14. Council approved construction 10/18/16. Council approved change order #1 2/21/17. Council approved new contract 5/16/17. Council approved change order #2 10/3/17. Council approved change order #3 1/16/18. 
Design Complete.

Under Construction.

Estimated Construction Completion Winter 2018.