Project Description: Line improvements from Richland Fashion Mall at Forest Dr to Lake Katherine near Kilbourne Road. Approximately 11,600 feet of new 24" gravity sewer. Total Current Contract Value is $2,048,471.49.

  • Council District: III, IV & Outside
  • Sewer Basin: Gills Creek

Public Benefit: Development Opportunity; Efficient Operations.

Project Map Project Gallery
Gallery Not Available
  • Project Status
  • Project Schedule
  • Project Events
Council approved design 3/18/14.
Estimated Design Completion Spring 2018.

Estimated Construction Start Summer 2018.

Estimated Construction Completion Summer 2020.