Project Description: Replacement and Upgrades to 6 existing pump stations-Clearwater, Yacht Cove, Meadowlands, Prescott Manor, Shady Lane, and Swandale Pump Stations.  Improvements include new wet wells, pumping, electrical and SCADA equipment, generator, larger easements or property, and other general site improvements. Total Current Contract Value is $4,044,007.10.

Public Benefit: Efficient Operations; Regulatory Compliance.

Project Map Project Gallery
  • Project Status
  • Project Schedule
  • Project Events
Council approved design 2/7/2012. Council approved construction 5/17/2016. Council approved contract amendment #3 6/7/2016.
Under Construction.

Estimated Construction End Winter 2017.