A Program Of The

City Of Columbia

Project Description: Major improvements to reduce I/I in the Olympia subbasin and prevent stormwater discharges into sewer system thus reducing SSOs. Total Current Contract Value is $3,837,856.43.

  • Council District: II, III & Outside
  • Sewer Basin: Rocky Branch

Public Benefit: Efficient Operations; Environmental; Regulatory Compliance.

Project Map Project Gallery
  • Project Status
  • Project Schedule
  • Project Events
Council approved design 8/19/14.
Estimated Design End Spring 2018.

Estimated Construction Start Spring 2019.

Estimated Construction End Spring 2020.